Total megawatts of U.S. nuclear capacity offline right now (units in outages plus reduced power).
4,482
MW Offline
Percentage of total fleet capacity currently online and generating power.
95.4%
Fleet Online
Refueling outages scheduled for this season. Each one is a hiring window.
24
Fall 2026 Outages
Units currently at 0% power (likely in an outage or shutdown).
4
Units Offline
Units operating between 1-99% power (excluding known startups or coastdowns).
0
Reduced Power
Units nearing the end of their fuel cycle, gradually lowering power before an outage.
6
Coastdown
Units increasing power following an outage or scram.
0
Starting Up
Units on a qualifying Breaker-to-Breaker run: continuous operation exceeding their cycle-adjusted threshold with no trips to 0% power.
13
Breaker-to-Breaker
Outage NewsNEW Davis-Besse trips offline, unscheduled outage underwayDavis-Besse began an unscheduled forced short outage on 2026-09-08. This event ended the unit's unscheduled-outage-free streak at 386 days. This is the first forced outage for the 894-MW Babcock and Wilcox PWR in 2026, matching the total count for all of 2025. Energy Harbor Nuclear Generation operates this unit along with three other U.S. nuclear units. Across the industry, 94 units are currently operating at a 95.4 percent capacity factor. Two units are currently in refueling outages, while Davis-Besse and Dresden 2 are the only two units in unscheduled outages at this time. OAK HARBOR, OH. An unscheduled outage at Davis-Besse began on Sep 8, 2026 . The NRC has not yet issued an event notification for this trip; a follow-up reply will be posted here if one is filed. This is the first unsc...
Outage NewsNEW North Anna 2 begins Fall 2026 refueling outageNorth Anna 2 began its scheduled refueling outage on September 6, 2026, two days earlier than the original plan. The unit entered this maintenance period after completing 95 percent of its typical 548-day operating cycle and maintaining an unscheduled-outage-free streak of 987 days. The unit is a 944-MW Westinghouse 3-loop PWR operated by Virginia Electric and Power, which manages three other nuclear units in the United States. This refueling follows a prior cycle that achieved a 90 percent capacity factor. The outage duration is scheduled for 36 days, compared to the 43-day average recorded a...
Outage NewsNEW McGuire 1 begins Fall 2026 refueling outageMcGuire 1 began its scheduled refueling outage on September 5, 2026, meeting the planned start date exactly. The unit entered this maintenance period after completing 92 percent of its typical 547-day operating cycle and maintaining an unscheduled-outage-free streak of 246 days. The 1,158-MW Westinghouse 4-loop PWR has a historical average refuel duration of 37.6 days across 18 prior events, with a maximum duration of 78 days recorded in 2007. Duke Energy Carolinas operates this unit along with six other U.S. nuclear units. Across the current fleet of 94 units, the industry capacity factor is...
Nuclear NewsNEW Fresh record set for nuclear generation in 2025Global nuclear electricity generation reached 2,702 TWh in 2025, surpassing the previous year's record. The global fleet maintained an average capacity factor of 83.7 percent, while construction began on eleven new reactors. To meet international goals of tripling capacity by 2050, the World Nuclear Association recommends that governments prioritize supply chain strengthening, regulatory streamlining, and the development of a skilled workforce to support sustained deployment. Nuclear reactors worldwide generated 2,702 TWh of electricity in 2025, beating the previous year's record of 2,667 TWh, according to the World Nuclear Outlook Report, which also calculates that if all national nuclear targets were achieved, total capacity would more than triple by 2050. ; The World Nuclear Association...
Nuclear NewsNEW New York’s big new bet on nuclear energyGov. Hochul, a Democrat, diluted New York’s climate law this year amid struggles to build large-scale renewables. Now, she’s looking to nuclear power. Read the full article at Canary Media :
Nuclear NewsNEW Utilities eye small modular nuclear reactors for reliability as hyperscalers drive demandTechnology companies and defense installations are leading the adoption of small modular reactors and microreactors to secure reliable, low-carbon power. Utilities are exploring these technologies through three-party agreements that share financial risk, though they remain constrained by existing grid infrastructure, long interconnection timelines, and the need for supportive state legislative frameworks. The industry is shifting from prototype testing toward commercial deployment by standardizing designs to reduce costs. While developers focus on fleet-scale construction, stakeholders note th...
Nuclear SoftwareNEW Looking for Rados softwareUpdate: I found out that Mirion bought Rados. I called Mirion and they informed me that they have discontinued the model and software. I haven't had any luck by reaching out to third parties.You're my only hope Obi-Wan :)
History & TriviaThe Hiroshima Atomic Blast Forged a Metal Never Seen Before on EarthGeologists led by the University of Florence have identified a previously unknown iron-chromium alloy within microscopic fallout debris from the 1945 Hiroshima atomic bombing. The 10-micrometer grain exhibits a complex, highly ordered cubic crystal structure that formed due to the extreme temperatures and rapid cooling rates of the nuclear fireball. This discovery highlights that nuclear blast debris contains a unique library of metastable materials that are difficult to replicate in laboratory settings. For the nuclear industry, these findings demonstrate that fallout particles serve as a phy...
DC CookNewly Renovated Furnished 2Br rental near D.C. CookD.C. Cook outage housing available in Stevensville for September/October.We have furnished 2BR / 1.5BA units available for outage workers, with full kitchen, in-unit washer/dryer, Wi-Fi, utilities, and parking included. Each unit has 1 king bed and 2 queen beds and works well for 1–2 workers or coworkers sharing a unit.Weekly and 4–6 week stays available. We also have two neighboring units, so we may be able to accommodate a small crew that wants to stay close together while still having separate living space.Located in Stevensville with convenient access to D.C. Cook.Message me for availability, photos, and outage-worker rates.goosewalrusstays@gmail.comTim973-997-8024









Every Outage Finally Has a NameIf you have worked an outage, you know it has a name. Nobody at the tool crib says &qu...
New on the facility map: see who's hiring at a glanceThe facility map got a pretty good overhau...
Did You Know NukeWorker Has Online Practice Exams? (Now With Certificates)Here is something a lot of folk...
The NukeWorker Reactor Status MapIf you have ever wanted to know which plants are running, which are down for an outa...
We have recently updated the with over 1,500 new aerial and facility images.Some of the late...
The Fall 2026 U.S. nuclear refueling outage schedule has been released. 25 units are scheduled to refuel this season.
POET: plant-specific PRA inputs, built from the operating recordA new tool on NukeWorker turns the U.S. fleet's...
We've launched a new board, Outage News: a running record of refueling and forced outages across ...
New Feature: RadNet Radiation Map Now OnlineWe're excited to announce a major addition to the Facility Info...
We have updated the "Current Reactor Status" section on our facility information pages ...
🔎 Deep Dive: Everything You Can Track on the Facility Info PagesHey everyone, I've been digging thr...
The Nuclear Grid Capacity & Generation Analysis dashboard provides a centralized interface for monitoring and...
We made a new tool fro you:The Operating Reactor Scram Dashboard is a comprehensive analytical tool designed fo...
I am very excited to announce a major upgrade to the NukeWorker Outage Schedules!We now independently project...
NukeWorker's preliminary schedule for Spring 2027 projects 29 nuclear outages, signaling a high-d...
The Fall 2026 nuclear maintenance season features 25 scheduled outages, with peak workload activity proje...
The Spring 2026 nuclear outage season is underway with 34 scheduled maintenance and refueling outages. View the full schedule at .
We've given the entire quiz section a major facelift to make your study sessions smoother and easier on the eyes.
The NukeWorker Photo Gallery has long been the primary destination for our community to share the history, te...
We've just rolled out a major update to the NukeWorker homepage. While the new "Situation Room&quo...
I split the 'Nuclear Discussions' from the 'Nuclear News' posts on the front page.Enhanced the titl...
I've updated the homepage Job Feed with a few key features designed to make it fairer for employers and easier for ...