Prediction Explanation: Palo Verde 1

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 539.0 +20.11 days
Containment Type PWR-DRYAMB -7.42 days
State AZ -3.97 days
Prior Cycle Length (months) 17.7 -2.97 days
Reactor Type (NSSS) COMB CE80 +1.55 days
Years to License Expiration 18.7 -1.3 days
unit_modal_month 10.0 -1.26 days
Fleet Outages This Year 1.0 +0.8 days
Years Since Major Maintenance 20.6 +0.78 days
unit_pct_in_predicted_month 0.1 -0.73 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?