Prediction Explanation: Browns Ferry 3
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
735.0 |
-53.73 days |
| Containment Type |
BWR-MARK 1 |
+27.18 days |
| Reactor Type (NSSS) |
GE |
+6.2 days |
| Prior Cycle Length (months) |
24.2 |
+4.52 days |
| Years to License Expiration |
28.4 |
+4.38 days |
| State |
Al |
-3.35 days |
| unit_pct_in_predicted_month |
0.6 |
+3.1 days |
| Units at Site |
3.0 |
-2.11 days |
| Forced Outage Days in Cycle |
33.0 |
-1.17 days |
| unit_pct_in_winter |
0.6 |
+1.1 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?
Page created in 0.005 seconds with 0 queries.