Projection Explanation: Brunswick 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 745.0 -60.12 days
Containment Type BWR-MARK 1 +25.76 days
Prior Cycle Length (months) 24.5 +4.99 days
Reactor Type (NSSS) GE 4 +3.41 days
unit_pct_in_predicted_month 0.6 +2.69 days
State NC +1.96 days
unit_pct_in_spring_fall 0.4 +1.58 days
unit_pct_in_winter 0.6 +1.49 days
3-Outage Rolling Avg Duration 34.7 -1.4 days
Units at Site 2.0 -1.14 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?