Projection Explanation: Byron 1
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
539.0 |
+22.32 days |
| Containment Type |
PWR-DRYAMB |
-8.01 days |
| Reactor Type (NSSS) |
WEST 4LP |
-4 days |
| Years to License Expiration |
17.2 |
-2.25 days |
| Prior Cycle Length (months) |
17.7 |
-1.87 days |
| unit_pct_in_predicted_month |
0.0 |
-1.63 days |
| Units at Site |
2.0 |
-1.4 days |
| State |
IL |
-0.94 days |
| Outage Number (experience) |
19.0 |
-0.54 days |
| Avg Coastdown Days (this unit) |
14.8 |
+0.51 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?