Projection Explanation: Callaway

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 546.0 +16.32 days
Containment Type PWR-DRYAMB -9 days
Reactor Type (NSSS) WEST 4LP -8.75 days
Avg Outages Between Major Maint. 2.3 -4.68 days
Units at Site 1.0 +3.46 days
NRC Region 4.0 -2.59 days
State MO +1.76 days
3-Outage Rolling Avg Duration 63.0 +1.69 days
Outage Number (experience) 18.0 -1.39 days
Net Capacity (MWe) 1190.0 -1.33 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?