Prediction Explanation: Cooper

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 728.0 -47.89 days
Containment Type BWR-MARK 1 +26.93 days
Reactor Type (NSSS) GE 4 +7.17 days
Years to License Expiration 7.3 +4.85 days
Units at Site 1.0 +4.58 days
Avg Outages Between Major Maint. 3.5 -3.8 days
State NE +2.82 days
Prior Cycle Length (months) 23.9 +1.85 days
Age at Outage (years) 52.2 -1.35 days
Fleet Outages This Year N/A +1.3 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?