Projection Explanation: D.C. Cook 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 546.0 +15.83 days
Containment Type PWR-ICECND -8.75 days
Reactor Type (NSSS) WEST 4LP -8.4 days
Architect-Engineer AEP +5.26 days
Fleet Density N/A +2.35 days
State MI +1.89 days
Forced Outage Days in Cycle 3.0 -1.85 days
Outage Number (experience) 17.0 -1.63 days
Net Capacity (MWe) 1168.0 -1.6 days
Avg Outages Between Major Maint. 2.5 -1.44 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?