Prediction Explanation: Farley 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 525.0 +32.07 days
Containment Type PWR-DRYAMB -7.68 days
Prior Cycle Length (months) 17.3 -4.08 days
State AL -2.28 days
Reactor Type (NSSS) WEST 3LP -2.05 days
Years to License Expiration 14.5 -1.65 days
Units at Site 2.0 -0.94 days
unit_pct_in_predicted_month 0.1 -0.92 days
Previous Outage Duration 35.0 +0.48 days
Avg Outages Between Major Maint. 8.5 -0.47 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?