Projection Explanation: Harris 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 542.0 +19.35 days
Containment Type PWR-DRYAMB -8.5 days
Units at Site 1.0 +4.28 days
Reactor Type (NSSS) WEST 3LP -3.57 days
Balancing Authority CPLE +2.76 days
Years to License Expiration 19.6 -2.37 days
Fleet Outages This Year 4.0 -2.35 days
Avg Outages Between Major Maint. N/A +1.76 days
Prior Cycle Length (months) 17.8 -1.67 days
Licensed Capacity (MWt) 2948.0 -1.24 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?