Prediction Explanation: LaSalle 1

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 721.0 -34.53 days
Containment Type BWR-MARK 2 +20.88 days
Reactor Type (NSSS) GE 5 +6.92 days
Prior Cycle Length (months) 23.7 +4.75 days
unit_pct_in_predicted_month 0.8 +3.21 days
Units at Site 2.0 -1.74 days
unit_pct_in_winter 1.0 +1.27 days
State IL -1.21 days
Years to License Expiration 14.2 -0.78 days
Net Capacity (MWe) 1131.0 -0.76 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?