Prediction Explanation: Millstone 2
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Containment Type |
PWR-DRYAMB |
-14.12 days |
| Cycle Length (days) |
556.0 |
+12.19 days |
| State |
CT |
-5.69 days |
| Prior Cycle Length (months) |
18.3 |
-5.53 days |
| Years to License Expiration |
7.8 |
+3 days |
| Units at Site |
2.0 |
-2.11 days |
| Reactor Type (NSSS) |
COMB CE |
+1.78 days |
| Balancing Authority |
ISNE |
-1.31 days |
| Owner |
Dominion Energy |
+1.19 days |
| Fleet Outages This Year |
3.0 |
-1.06 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?