Prediction Explanation: Quad Cities 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 742.0 -58.08 days
Containment Type BWR-MARK 1 +25.79 days
Years to License Expiration 4.7 +7.78 days
Reactor Type (NSSS) GE 3 +4.43 days
Prior Cycle Length (months) 24.4 +4.41 days
unit_pct_in_predicted_month 0.7 +2.95 days
Age at Outage (years) 55.0 -1.78 days
Units at Site 2.0 -1.7 days
State IL -1 days
3-Outage Rolling Avg Duration 26.7 -0.68 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?