Projection Explanation: Saint Lucie 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Containment Type PWR-DRYAMB -13.37 days
Years to License Expiration 28.9 +7.74 days
State FL -6.82 days
Cycle Length (days) 560.0 +3.73 days
Reactor Type (NSSS) COMB CE +2.24 days
Outage Number (experience) 18.0 -0.98 days
cycle_interval_std 19.3 -0.91 days
Units at Site 2.0 -0.9 days
Balancing Authority FPL -0.8 days
Architect-Engineer EBSO -0.78 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?