Prediction Explanation: Saint Lucie 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 595.0 -14.94 days
Containment Type PWR-DRYAMB -14.56 days
Prior Cycle Length (months) 19.6 -11.27 days
State FL -7.73 days
Years to License Expiration 35.5 +6.8 days
unit_pct_in_predicted_month 0.0 -4.83 days
unit_pct_in_summer 0.2 -3.9 days
Reactor Type (NSSS) COMB CE +3.66 days
Net Capacity (MWe) 987.0 -1.45 days
Owner NextEra Energy -1.15 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?

Page created in 0.009 seconds with 0 queries.