Prediction Explanation: Salem 2
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
546.0 |
+15.55 days |
| Containment Type |
PWR-DRYAMB |
-8.51 days |
| Reactor Type (NSSS) |
WEST 4LP |
-6.4 days |
| Prior Cycle Length (months) |
18.0 |
-2.37 days |
| Years to License Expiration |
12.5 |
-1.88 days |
| State |
NJ |
+1.74 days |
| Units at Site |
2.0 |
-0.99 days |
| Fleet Outages This Year |
1.0 |
+0.89 days |
| Net Capacity (MWe) |
1142.0 |
-0.78 days |
| Avg Outages Between Major Maint. |
5.0 |
-0.5 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?