Prediction Explanation: Salem 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 546.0 +15.55 days
Containment Type PWR-DRYAMB -8.51 days
Reactor Type (NSSS) WEST 4LP -6.4 days
Prior Cycle Length (months) 18.0 -2.37 days
Years to License Expiration 12.5 -1.88 days
State NJ +1.74 days
Units at Site 2.0 -0.99 days
Fleet Outages This Year 1.0 +0.89 days
Net Capacity (MWe) 1142.0 -0.78 days
Avg Outages Between Major Maint. 5.0 -0.5 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?