Projection Explanation: Turkey Point 4

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 518.0 +39.32 days
Containment Type PWR-DRYAMB -6.93 days
Prior Cycle Length (months) 17.0 -3.78 days
State FL -3.59 days
unit_pct_in_predicted_month 0.0 -2.76 days
Reactor Type (NSSS) WEST 3LP -2.24 days
Licensed Capacity (MWt) 2644.0 -1.97 days
Years to License Expiration 26.6 -1.84 days
Units at Site 2.0 -1.84 days
Age at Outage (years) 53.0 -1.34 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?