Prediction Explanation: Waterford 3
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Containment Type |
PWR-DRYAMB |
-17.29 days |
| Cycle Length (days) |
560.0 |
+15.19 days |
| Units at Site |
1.0 |
+10.43 days |
| Prior Cycle Length (months) |
18.4 |
-6.76 days |
| Avg Outages Between Major Maint. |
2.4 |
-5 days |
| Previous Outage Duration |
110.0 |
-3.06 days |
| State |
LA |
-3.04 days |
| Reactor Type (NSSS) |
COMB CE |
+2.91 days |
| Forced Outage Days in Cycle |
61.0 |
-2.88 days |
| Fleet Outages This Year |
1.0 |
+2.54 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?
Page created in 0.005 seconds with 0 queries.