Projection Explanation: Watts Bar 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
525.0 |
+32.99 days |
| Years to License Expiration |
29.0 |
+16.36 days |
| Outage Number (experience) |
6.0 |
+10.78 days |
| Containment Type |
PWR-ICECND |
-5.98 days |
| Reactor Type (NSSS) |
WEST 4LP |
-3.52 days |
| 3-Outage Rolling Avg Duration |
57.7 |
+3.47 days |
| unit_n_prior_refuels |
5.0 |
+3.22 days |
| Licensed Capacity (MWt) |
3459.0 |
-3.02 days |
| unit_pct_in_predicted_month |
0.4 |
-3.02 days |
| State |
TN |
+2.87 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?