Prediction Explanation: Wolf Creek 1

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 553.0 +14.95 days
Containment Type PWR-DRYAMB -14.45 days
Reactor Type (NSSS) WEST 4LP -6.56 days
Avg Outages Between Major Maint. 1.2 -4.08 days
Units at Site 1.0 +2.93 days
Prior Cycle Length (months) 18.2 -2.34 days
Owner Wolf Creek Nuclear +2.31 days
State KS -1.86 days
Years to License Expiration 17.9 -1.55 days
Fleet Outages This Year N/A +0.9 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?