Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
3 units: 2 operational, 1 under construction.
Net capacity in service: 1,884 MWe.
| Unit | Type | Model | Net MWe | Construction | Grid | Commercial Op | Shutdown | Status |
|---|---|---|---|---|---|---|---|---|
| Angra 1 | PWR | WH 2LP | 609 | 1971-05-01 | 1982-04-01 | 1985-01-01 | Operational | |
| Angra 2 | PWR | PRE KONVOI | 1,275 | 1976-01-01 | 2000-07-21 | 2001-02-01 | Operational | |
| Angra 3 | PWR | PRE KONVOI | 1,340 | 2010-05-30 | 2033-07-14 | 2033-11-01 | Under Construction |
Capacity, milestones and suppliers
| Unit | Design MWe | Gross MWe | Thermal MWt | First Criticality | Reactor Supplier | Turbine Supplier | Notes |
|---|---|---|---|---|---|---|---|
| Angra 1 | 626 | 640 | 1,882 | 1982-03-13 | WESTINGHOUSE ELECTRIC CORPORATION | WESTINGHOUSE ELECTRIC CORPORATION | |
| Angra 2 | 1,245 | 1,350 | 3,764 | 2000-07-14 | KRAFTWERK UNION, AG | KRAFTWERK UNION, AG | |
| Angra 3 | 1,340 | 1,405 | 3,900 | 2033-07-04 | KRAFTWERK UNION, AG | KRAFTWERK UNION, AG |
Lifetime performance, through 2025
| Unit | Electricity Supplied | Load Factor | Energy Availability | Operating Factor |
|---|---|---|---|---|
| Angra 1 | 132.6 TWh | 59.3% | 65.5% | 71.8% |
| Angra 2 | 240.2 TWh | 85.0% | 86.8% | 88.7% |
Operator: ELETRONUCLEAR S.A.
Owner: ELETRONUCLEAR S.A.
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-14.
Fuel Cycle Facilities
Fuel cycle plants at this site, as listed in the IAEA Nuclear Fuel Cycle Facilities Database: what each plant does, its scale and design capacity, the years it operated, its current status and who operates it.
3 facilities: 3 in operation.
| Facility | Type | Scale | Design Capacity | Operated | Status | Operator |
|---|---|---|---|---|---|---|
| internal storage facility (KPE located in UKA Building ANGRA-2) | AFR Wet Spent Fuel Storage (Pool) | Commercial | 1644 t HM | 2001– | In Operation | Electronuclear |
| Irradiated fuel dry complementary Storage unit | AFR Dry Spent Fuel Storage | Commercial | 2021– | In Operation | Electronuclear | |
| OLD STEAM GENERATORS STORAGE FACILITY (ANGRA-1) | Waste Management Facilities | Commercial | In Operation | Electronuclear |
Source: IAEA Nuclear Fuel Cycle Facilities Database (NFCFDB), as of 2026-10-13.
Working Here
Per Diem Rates FY 2026
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$262
Lodging/Night
$113
M&IE/Day
$375
Total/Day
Brazil: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.
Photos
Photos of this facility from the NukeWorker photo gallery. Click the header or any photo to browse the full album.
Facility Map
Interactive satellite map showing the facility's geographic location. Marker color indicates current status: green for online, red for offline, orange for reduced power. Click the header to open in Google Maps satellite view.
-23.0069, -44.4579
Location & Contact
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Plant Facts
About This Site
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Angra Nuclear Power Plant.
Angra is a nuclear power plant complex on Itaorna Beach in Angra dos Reis, Rio de Janeiro state, Brazil, on the Atlantic coast.
Read more
A comprehensive nuclear agreement with West Germany was signed in 1975. Angra 1, a Westinghouse pressurized water reactor, began construction on 1 May 1971, reached first criticality on 3 March 1982 and was connected to the grid on 1 April 1982. Angra 2, a Siemens design, began construction on 1 January 1976, reached criticality on 14 July 2000 and was connected to the grid on 21 July 2000. Angra 3, also a Siemens/KWU design, was developed from 1984 and construction was halted in 1986.