Fermi 1

SAFSTOR

DTE Energy·Monroe, MI·FBR·65 MWe

Community ratings, technical specifications, photos, nearby jobs, satellite map, contact information, and per diem rates for Fermi 1.

SAFSTOR

Permanently shut down on 1972-11-29.

Reactor Data

Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
1 unit: 1 permanent shutdown.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Fermi 1 FBR Liquid Metal FBR 60 1956-08-08 1966-08-05 1966-08-07 1972-11-29 Permanent Shutdown
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Fermi 1 60 65 200 1963-08-23 UNITED ENGINEERS AND CONTRACTORS GENERAL ELECTRIC CO.
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Fermi 1 0.0 TWh 3.7% 100.0% 0.0%
Operator: DETROIT EDISON CO.
Owner: Power Reactor Development Company (PRDC), consortium of 34 public utilities
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-14.

Working Here

Per Diem Rates FY 2027

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from GSA for FY 2027.
$113
Lodging/Night
$68
M&IE/Day
$181
Total/Day
Standard Rate, MI

Unemployment Benefits MI

?
Maximum state unemployment insurance benefits for MI. Actual benefits depend on your earnings history and may be lower than the maximum. Data as of Jan 2026.
$530
Max Weekly
26
Max Weeks
$13,780
Max Total

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
6400 North Dixie Highway
Monroe, MI 48162, USA
Get Directions
Phone: (313) 586-5300

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Enrico Fermi Nuclear Generating Station.

Enrico Fermi Nuclear Generating Station is a nuclear power site in Frenchtown Charter Township, Monroe County, Michigan, on the shore of Lake Erie. It has had two units: Fermi 1, a sodium-cooled fast breeder prototype, and Fermi 2, a boiling water reactor.

Read more

Fermi 1 was built starting in 1956 and first went critical on August 23, 1963. It was connected to the grid on August 5, 1966. On October 5, 1966, a partial fuel meltdown occurred. The unit restarted in July 1970, was shut down permanently on November 29, 1972, and was officially decommissioned on December 31, 1975. Fermi 2 is a General Electric BWR-4. Construction began on September 26, 1972, it was connected to the grid on September 21, 1986, and it entered commercial operation on January 23, 1988.

Ownership & Construction

?
The utility or company that owns and operates the facility, the architect-engineer responsible for plant design, and the primary construction contractor. Click names to view all facilities by that entity on the map.
Owner/Operator: DTE Energy
DTE DTE Energy Company NYSE
$129.73 ▲ +1.40 (+1.09%)
Previous Close 128.33
Day's Range 128.08 – 129.97
52-Week Range 119.68 – 155.75
Volume 2,103,587
Delayed quote as of Oct 16, 2026 4:02 PM ET. Source: Yahoo Finance. Full quote on Yahoo Finance

Technical Specs

?
Reactor design specifications including type (PWR/BWR), containment design, nuclear steam supply system manufacturer, thermal and electrical power ratings, and current operational status.
Reactor Type: FBR
NSS Supplier: UEC
Net Capacity: 65 MWe
Status: SAFSTOR

Licensing

?
NRC licensing history including docket number, license type and number, construction permit date, operating license issuance, commercial operation date, license renewal, and expiration date.
Const. Permit: 1956-08-01
Operating Lic: 1966-08-05