Goesgen

Technical specifications, photos, nearby jobs, and satellite map for Goesgen.

Reactor Data

Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
1 unit: 1 operational. Net capacity in service: 1,010 MWe.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Goesgen PWR PWR 3 Loop 1,010 1973-12-01 1979-02-02 1979-11-01 Operational
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Goesgen 920 1,060 3,002 1979-01-20 KRAFTWERK UNION, AG KRAFTWERK UNION, AG
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Goesgen 340.6 TWh 88.2% 87.9% 89.6%
Operator: KERNKRAFTWERK GÖSGEN-DÄNIKEN AG
Owner: KERNKRAFTWERK GÖSGEN-DÄNIKEN AG
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-26.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$292
Lodging/Night
$195
M&IE/Day
$487
Total/Day
Switzerland: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Däniken, Solothurn, Switzerland
Get Directions

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Goesgen Nuclear Power Plant.

Goesgen is a nuclear power plant at Däniken, in the canton of Solothurn, Switzerland, on a loop of the Aare river.

Read more

A 1971 federal decision banned river-water cooling for new plants, so a cooling tower was added to the design. Location authorization was issued on 31 October 1972 and construction began in 1973. The single pressurized water reactor was supplied by Kraftwerk Union (Siemens). It was connected to the grid on 2 February 1979, and commercial operation began on 1 November 1979 after a safety review that followed the Three Mile Island accident. Large protests took place between 1977 and 1981.