Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
4 units: 3 operational, 1 permanent shutdown. Net capacity in service: 2,637 MWe.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Kori 1 PWR WH 60 576 1972-08-01 1977-06-26 1978-04-29 2017-06-18 Permanent Shutdown
Kori 2 PWR WH F 640 1977-12-23 1983-04-22 1983-07-25 Operational
Kori 3 PWR WH F 996 1979-10-01 1985-01-22 1985-09-30 Operational
Kori 4 PWR WH F 1,001 1980-04-01 1985-12-31 1986-04-29 Operational
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Kori 1 558 607 1,729 1977-06-19 WESTINGHOUSE ELECTRIC CORPORATION GENERAL ELECTRIC COMPANY (UK)
Kori 2 618 681 1,882 1983-04-09 WESTINGHOUSE ELECTRIC CORPORATION GENERAL ELECTRIC COMPANY (UK)
Kori 3 1,011 1,046 2,912 1985-01-01 WESTINGHOUSE ELECTRIC CORPORATION GENERAL ELECTRIC COMPANY (UK)
Kori 4 903 1,046 2,912 1985-10-26 WESTINGHOUSE ELECTRIC CORPORATION GENERAL ELECTRIC COMPANY (UK)
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Kori 1 148.6 TWh 76.0% 78.8% 79.5%
Kori 2 185.2 TWh 79.5% 78.4% 79.4%
Kori 3 274.5 TWh 81.4% 79.8% 80.6%
Kori 4 279.9 TWh 84.1% 82.4% 83.1%
Operator: Korea Hydro and Nuclear Power Co.
Owner: Korea Hydro and Nuclear Power Co.
Source: IAEA Power Reactor Information System (PRIS), as of 2026-11-02.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$60
Lodging/Night
$40
M&IE/Day
$100
Total/Day
South Korea: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Gijang, Busan, South Korea
Get Directions

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Kori Nuclear Power Plant.

Kori Nuclear Power Plant is at Gori (Kori), a coastal village in the Gijang area of Busan, South Korea, on the Sea of Japan.

Read more

Construction of Unit 1 began on 1 August 1972, followed by Unit 2 on 23 December 1977, Unit 3 on 1 October 1979 and Unit 4 on 1 April 1980. All four are Westinghouse-type pressurized water reactors. Unit 1 was connected to the grid on 26 June 1977 and entered commercial operation on 29 April 1978. During a refueling outage on 9 February 2012 the plant lost off-site power for about 12 minutes, and the event was reported a month late. Unit 1 was permanently shut down on 18 June 2017.