Reactor Data

Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
8 units: 4 operational, 2 under construction, 2 permanent shutdown. Net capacity in service: 4,052 MWe.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Leningrad 1 LWGR RBMK-1000 925 1970-03-01 1973-12-21 1974-11-01 2018-12-21 Permanent Shutdown
Leningrad 2 LWGR RBMK-1000 925 1970-06-01 1975-07-11 1975-11-11 2020-11-10 Permanent Shutdown
Leningrad 3 LWGR RBMK-1000 925 1973-12-01 1979-12-07 1980-06-29 Operational
Leningrad 4 LWGR RBMK-1000 925 1975-02-01 1981-02-09 1981-08-29 Operational
Leningrad 2-1 PWR VVER V-491 1,101 2008-10-25 2018-03-09 2018-10-24 Operational
Leningrad 2-2 PWR VVER V-491 1,101 2010-04-15 2020-10-22 2021-03-18 Operational
Leningrad 2-3 PWR VVER V-491 1,064 2024-03-14 2030-03-06 2030-10-20 Under Construction
Leningrad 2-4 PWR VVER V-491 1,064 2025-03-20 2032-03-06 2032-10-20 Under Construction
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Leningrad 1 925 1,000 3,200 1973-09-12 Atomenergomash Kharkiv Turbine Factory Decommissioning from 2025-12-23
Leningrad 2 925 1,000 3,200 1975-05-06 Atomenergomash Kharkiv Turbine Factory
Leningrad 3 925 1,000 3,200 1979-09-17 Atomenergomash Kharkiv Turbine Factory
Leningrad 4 925 1,000 3,200 1980-12-29 Atomenergomash Kharkiv Turbine Factory
Leningrad 2-1 1,106 1,188 3,200 2018-02-06 Atomenergomash Atomenergomash
Leningrad 2-2 1,106 1,188 3,200 2020-08-29 Atomenergomash Atomenergomash
Leningrad 2-3 1,064 1,150 3,200 2029-12-11 Atomenergomash Atomenergomash
Leningrad 2-4 1,064 1,150 3,200 2031-12-13 Atomenergomash Atomenergomash
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Leningrad 1 244.1 TWh 67.4% 67.9% 73.1%
Leningrad 2 255.7 TWh 69.9% 70.2% 75.8%
Leningrad 3 272.2 TWh 73.0% 73.9% 76.6%
Leningrad 4 263.7 TWh 74.6% 75.3% 77.9%
Leningrad 2-1 54.0 TWh 75.1% 76.2% 77.8%
Leningrad 2-2 40.5 TWh 82.7% 82.5% 85.0%
Operator: Joint Stock Company 'Concern Rosenergoatom'
Owner: Joint Stock Company 'Concern Rosenergoatom'
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-12.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$173
Lodging/Night
$112
M&IE/Day
$285
Total/Day
Russia: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Sosnoviy Bor, Leningrad Oblast, Russia
Get Directions