Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
3 units: 1 operational, 2 permanent shutdown. Net capacity in service: 780 MWe.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Mihama 1 PWR WH 2LP 320 1967-02-01 1970-08-08 1970-11-28 2015-04-27 Permanent Shutdown
Mihama 2 PWR M (2-loop) 470 1968-05-29 1972-04-21 1972-07-25 2015-04-27 Permanent Shutdown
Mihama 3 PWR M (3-loop) 780 1972-08-07 1976-02-19 1976-12-01 Operational
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Mihama 1 320 340 1,031 1970-07-29 WESTINGHOUSE ELECTRIC CORPORATION MITSUBISHI HEAVY INDUSTRIES, LTD.
Mihama 2 470 500 1,456 1972-04-10 MITSUBISHI HEAVY INDUSTRIES, LTD. MITSUBISHI HEAVY INDUSTRIES, LTD.
Mihama 3 780 826 2,440 1976-01-28 MITSUBISHI HEAVY INDUSTRIES, LTD. MITSUBISHI HEAVY INDUSTRIES, LTD.
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Mihama 1 60.1 TWh 48.3% 47.5% 50.2%
Mihama 2 101.6 TWh 57.7% 57.6% 58.6%
Mihama 3 190.7 TWh 56.8% 56.0% 56.7%
Operator: Kansai Electric Power Co.
Owner: Kansai Electric Power Co.
Source: IAEA Power Reactor Information System (PRIS), as of 2026-11-02.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$208
Lodging/Night
$107
M&IE/Day
$315
Total/Day
Japan: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Mihama, Fukui Prefecture, Japan
Get Directions

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Mihama Nuclear Power Plant.

Mihama Nuclear Power Plant is in the town of Mihama, Fukui Prefecture, Japan, on Nyunoura Bay on the Sea of Japan.

Read more

Construction of Unit 1 began on 1 February 1967, Unit 2 on 29 May 1968 and Unit 3 on 7 August 1972. All three are pressurized water reactors, and Unit 3 is a Westinghouse-type three-loop design. Unit 1 was connected to the grid on 8 August 1970, Unit 2 on 21 April 1972 and Unit 3 on 19 February 1976. On 9 August 2004 a steam pipe burst in the Unit 3 turbine building, killing five workers and injuring six. Units 1 and 2 were permanently shut down on 27 April 2015.