Rancho Seco

DECON

SMUD·Herald, CA·PWR·873 MWe

Technical specifications, photos, nearby jobs, satellite map, contact information, and per diem rates for Rancho Seco.

DECON

Permanently shut down on 1989-06-07.

Reactor Data

Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
1 unit: 1 permanent shutdown.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Rancho Seco PWR PWR 873 1969-04-01 1974-10-13 1975-04-17 1989-06-07 Permanent Shutdown
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Rancho Seco 918 917 2,772 1974-09-16 BABCOCK & WILCOX CO. WESTINGHOUSE ELECTRIC CORPORATION
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Rancho Seco 44.8 TWh 39.9% 45.5% 46.3%
Operator: SACRAMENTO MUNICIPAL UTILITY DISTRICT
Owner: Sacramento Municipal Utility District
Source: IAEA Power Reactor Information System (PRIS), as of 2026-11-02.

Fuel Cycle Facilities

?
Fuel cycle plants at this site, as listed in the IAEA Nuclear Fuel Cycle Facilities Database: what each plant does, its scale and design capacity, the years it operated, its current status and who operates it.
2 facilities: 2 in operation.
Facility Type Scale Design Capacity Operated Status Operator
Rancho Seco NPP Site AFR Dry Spent Fuel Storage Commercial 190 t HM 1989– In Operation
Rancho Seco NPP Site ISFSI AFR Dry Spent Fuel Storage Commercial 202 t HM 1989– In Operation Sacramento Municipal Utility District
Source: IAEA Nuclear Fuel Cycle Facilities Database (NFCFDB), as of 2026-10-13.

Working Here

Per Diem Rates FY 2027

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from GSA for FY 2027.
$156
Lodging/Night
$86
M&IE/Day
$242
Total/Day
Sacramento, Sacramento County, CA

Unemployment Benefits CA

?
Maximum state unemployment insurance benefits for CA. Actual benefits depend on your earnings history and may be lower than the maximum. Data as of Jan 2026.
$450
Max Weekly
26
Max Weeks
$11,700
Max Total
7-day waiting period before benefits begin

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
14440 Twin Cities Road
Herald, CA 95638, USA
Get Directions
Phone: (916) 452-3211

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Rancho Seco Nuclear Generating Station.

Rancho Seco Nuclear Generating Station is in Herald, in southeast Sacramento County, California. The Sacramento Municipal Utility District (SMUD) bought the site in 1966 and built the plant, which had one Babcock & Wilcox pressurized water reactor.

Read more

The reactor first reached criticality on September 16, 1974, and began commercial operation on April 17, 1975. In June 1989, voters in the SMUD service area chose, 53 percent to 47 percent, to close the plant, mainly for economic reasons, and the reactor was permanently shut down that month. The NRC released most of the site for unrestricted use on October 23, 2009.

Ownership & Construction

?
The utility or company that owns and operates the facility, the architect-engineer responsible for plant design, and the primary construction contractor. Click names to view all facilities by that entity on the map.
Owner/Operator: SMUD
Publicly Traded No — Municipal utility district

Technical Specs

?
Reactor design specifications including type (PWR/BWR), containment design, nuclear steam supply system manufacturer, thermal and electrical power ratings, and current operational status.
Reactor Type: PWR
NSS Supplier: B&W
Net Capacity: 873 MWe
Status: DECON

Licensing

?
NRC licensing history including docket number, license type and number, construction permit date, operating license issuance, commercial operation date, license renewal, and expiration date.
Const. Permit: 1969-04-01
Operating Lic: 1974-10-13
Commercial Op: 1975-04-17