Reactor Data

Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
4 units: 4 operational. Net capacity in service: 1,160 MWe.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Tarapur 1 BWR BWR-1 (Mark 2) 150 1964-10-01 1969-04-01 1969-10-28 Operational
Tarapur 2 BWR BWR-1 (Mark 2) 150 1964-10-01 1969-05-05 1969-10-28 Operational
Tarapur 4 PHWR Horizontal Pressure Tube Type 378 2000-03-08 2005-06-04 2005-09-12 Operational
Tarapur 3 PHWR Horizontal Pressure Tube Type 482 2000-05-12 2006-06-15 2006-08-18 Operational
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Tarapur 1 200 160 530 1969-02-01 GENERAL ELECTRIC CO. GENERAL ELECTRIC CO. Suspended 2020-01-18; Restarted 2026-01-29
Tarapur 2 200 160 530 1969-02-28 GENERAL ELECTRIC CO. GENERAL ELECTRIC CO. Suspended 2020-07-13; Restarted 2026-06-06
Tarapur 4 502 540 1,730 2005-03-06 NUCLEAR POWER CORPORATION OF INDIA, LTD. Vikram Sarabhai Bhavan, Anushakti Nagar, Mumbai - 400 094. Bharat Heavy Electricals Ltd (BHEL) www.bhel.com
Tarapur 3 502 540 1,730 2006-05-21 NUCLEAR POWER CORPORATION OF INDIA, LTD. Vikram Sarabhai Bhavan, Anushakti Nagar, Mumbai - 400 094. Bharat Heavy Electricals Ltd (BHEL) www.bhel.com
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Tarapur 1 45.4 TWh 63.1% 67.4% 75.4%
Tarapur 2 47.0 TWh 64.2% 67.6% 75.2%
Tarapur 4 64.2 TWh 74.3% 75.1% 85.5%
Tarapur 3 66.9 TWh 80.5% 81.3% 88.8%
Operator: NUCLEAR POWER CORPORATION OF INDIA, LTD.
Owner: NUCLEAR POWER CORPORATION OF INDIA, LTD.
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-14.

Fuel Cycle Facilities

?
Fuel cycle plants at this site, as listed in the IAEA Nuclear Fuel Cycle Facilities Database: what each plant does, its scale and design capacity, the years it operated, its current status and who operates it.
2 facilities: 2 in operation.
Facility Type Scale Design Capacity Operated Status Operator
Tarapur (AFR) AFR Wet Spent Fuel Storage (Pool) Commercial 275 t HM 1990– In Operation Nuclear Power Corporation of India Ltd
Tarapur NPP Site AFR Dry Spent Fuel Storage Commercial 20 t HM 1990– In Operation Nuclear Power Corporation of India Ltd
Source: IAEA Nuclear Fuel Cycle Facilities Database (NFCFDB), as of 2026-10-13.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$196
Lodging/Night
$92
M&IE/Day
$288
Total/Day
India: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Boisar, Maharashtra, India
Get Directions

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Tarapur Atomic Power Station.

Tarapur Atomic Power Station is a nuclear power plant on the Arabian Sea coast in Palghar district, Maharashtra, India, near Boisar.

Read more

Its first two units are boiling water reactors built by General Electric and Bechtel under a 1963 agreement among India, the United States and the IAEA. Construction of those units began in the 1960s, and they were connected to the grid on 1 April and 5 May 1969. They were the first commercial nuclear power units in India. Construction of two Indian-designed 540 MW heavy water reactors began in 2000, with Unit 4 reaching the grid on 4 June 2005 and Unit 3 on 15 June 2006.