1 unit: 1 under construction.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Xuwei 1 PWR HPR1000 729 2026-01-16 Under Construction
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Xuwei 1 729 1,208 3,190 China First Heavy Industries Harbin Electric Co., Ltd.
Operator: CNNC SuNeng Nuclear Power Co., Ltd.
Owner: CNNC SuNeng Nuclear Power Co., Ltd.
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-19.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$170
Lodging/Night
$98
M&IE/Day
$268
Total/Day
China: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Lianyungang City, Jiangsu, China
Get Directions

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Xuwei Nuclear Power Plant; Nuclear Engineering International: Xuwei launches PWR-HTGR coupling project.

Xuwei is a nuclear power plant site at Xuwei, Lianyungang, on the coast of Jiangsu Province, China.

Read more

China's State Council approved Phase I in August 2024, together with a group of other new reactors. The approved design is two Hualong One pressurized water reactors and one HTR-PM600 high-temperature gas-cooled reactor, as a combined heat and power project linked to the petrochemical industry. First concrete for the Unit 1 nuclear island was poured on 16 January 2026.