Zhaoyuan

Technical specifications, photos, nearby jobs, and satellite map for Zhaoyuan.

Reactor Data

Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
1 unit: 1 under construction.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Zhaoyuan 1 PWR HPR1000 1,117 2025-11-18 Under Construction
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Zhaoyuan 1 1,117 1,214 3,190 China First Heavy Industries Harbin Electric Co., Ltd.
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-19.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$170
Lodging/Night
$98
M&IE/Day
$268
Total/Day
China: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Yantai City, Shandong, China
Get Directions

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Zhaoyuan Nuclear Power Plant.

Zhaoyuan is a nuclear power plant site at Zhangxing in Zhaoyuan, a county-level city of Yantai in Shandong Province, China. It lies a few kilometers inland, southeast of Laizhou Bay.

Read more

China's State Council approved the first two units in August 2024, as part of a group of eleven reactors approved together. The site uses the Hualong One pressurized water reactor design. Construction of Unit 1 began on 18 November 2025, with the pouring of first nuclear concrete.