Projection Explanation: Arkansas Nuclear 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
532.0 |
+25.54 days |
| Containment Type |
PWR-DRYAMB |
-7.74 days |
| State |
AR |
-5.47 days |
| Years to License Expiration |
10.8 |
-2.22 days |
| Prior Cycle Length (months) |
17.5 |
-2.06 days |
| Reactor Type (NSSS) |
COMB CE |
+1.56 days |
| NRC Region |
4.0 |
-1.16 days |
| Units at Site |
2.0 |
-0.92 days |
| unit_modal_month |
9.0 |
-0.79 days |
| Balancing Authority |
MISO |
-0.75 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?