Prediction Explanation: Byron 2
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
553.0 |
+13.68 days |
| Containment Type |
PWR-DRYAMB |
-13.08 days |
| Reactor Type (NSSS) |
WEST 4LP |
-6.51 days |
| Prior Cycle Length (months) |
18.2 |
-2.54 days |
| Units at Site |
2.0 |
-1.69 days |
| State |
IL |
-1.31 days |
| Years to License Expiration |
20.1 |
-1.09 days |
| Net Capacity (MWe) |
1136.0 |
-1.08 days |
| Age at Outage (years) |
39.2 |
+0.51 days |
| Fleet Outages This Year |
8.0 |
+0.45 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?