Projection Explanation: Byron 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
532.0 |
+27.73 days |
| Containment Type |
PWR-DRYAMB |
-9.25 days |
| Reactor Type (NSSS) |
WEST 4LP |
-4.94 days |
| Units at Site |
2.0 |
-1.37 days |
| Licensed Capacity (MWt) |
3645.0 |
-1.05 days |
| unit_pct_in_predicted_month |
0.1 |
-0.85 days |
| Net Capacity (MWe) |
1136.0 |
-0.82 days |
| State |
IL |
-0.78 days |
| Fleet Outages This Year |
11.0 |
+0.73 days |
| Outage Number (experience) |
19.0 |
-0.68 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?