Projection Explanation: Calvert Cliffs 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 735.0 -26.47 days
Prior Cycle Length (months) 24.2 +5.16 days
Reactor Type (NSSS) COMB CE +4.18 days
Containment Type PWR-DRYAMB -4.07 days
unit_pct_in_predicted_month 0.8 +2.84 days
Years to License Expiration 9.5 -1.74 days
unit_pct_in_spring_fall 0.2 +1.67 days
unit_pct_in_winter 0.8 +1.37 days
Units at Site 2.0 -1.26 days
Net Capacity (MWe) 861.0 +1.17 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?