Projection Explanation: Comanche Peak 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Containment Type PWR-DRYAMB -9.82 days
Cycle Length (days) 553.0 +9.57 days
Reactor Type (NSSS) WEST 4LP -4.66 days
Years to License Expiration 23.3 -3.11 days
State TX +2.67 days
Prior Cycle Length (months) 18.2 -1.64 days
Units at Site 2.0 -1.25 days
NRC Region 4.0 -1 days
Licensed Capacity (MWt) 3612.0 -0.9 days
Fleet Sequence Position N/A +0.78 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?