Prediction Explanation: Comanche Peak 1

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 553.0 +13.37 days
Containment Type PWR-DRYAMB -13.13 days
Reactor Type (NSSS) WEST 4LP -8.06 days
State TX +2.45 days
Prior Cycle Length (months) 18.2 -1.97 days
Net Capacity (MWe) 1205.0 -1.44 days
Years to License Expiration 23.3 -1.36 days
Units at Site 2.0 -1.25 days
Age at Outage (years) 36.2 +1.04 days
NRC Region 4.0 -0.55 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?