Comanche Peak 1 — Nuclear Reactor Data & Live Status

Live reactor status, daily power data, outage history & performance charts, scram history, capacity factor & statistics, community ratings, technical specifications, NRC licensing data, photos, nearby jobs, satellite map, contact information, and per diem rates for Comanche Peak 1.

?
Composite Operational Excellence Score (0-100) — average percentile rank across 7 dimensions in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). 5-year window. Higher = more operationally excellent. Click to see the full breakdown.
53
Excellence
#35 of 93
Mid Quartile
?
Current reactor power level from the most recent NRC daily report.
100%
Power
ONLINE
?
Days of continuous operation since the last outage ended. Ranked against all operating units.
342
Current Run
days
#24 of 95
Top Quartile
?
Longest recorded period of continuous operation between outages.
535
Record Run
days
#78 of 95
Bottom Quartile
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold (458 days for this 18-month cycle unit) with no trips to 0% power.
8
B2B Runs
#21 of 87
Top Quartile
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power). Ranked against all NRC-tracked units.
92.7%
Capacity Factor
#19 of 95
Top Quartile
?
Net electricity actually generated over the most recent 12 months reported by the U.S. Energy Information Administration (Form EIA-923), summed across every unit at this plant. These are authoritative actuals, not an estimate.
20.02 TWh
Net Generation
EIA-923 · 12 mo to 2026-06 · plant total
?
Community rating score (Bayesian-adjusted). Based on 52 votes. Ranked against all rated facilities.
71.9
Rating
52 votes
#2 of 97
Top Quartile
?
Total NRC-reported scram events (emergency reactor shutdowns). Ranked fleet-wide — fewer scrams = better rank.
5
Scrams
#26 of 94
Mid Quartile
?
Years since commercial operation began. License remaining: 23.4 years.
36.1
Operating Age
years
23.4 yrs remaining

Reactor Status Timeline

Online NRC data, Mon to Fri ? Actual daily reactor status from NRC reports (Mon to Fri) and the current state. What is coming -- the utility's published Scheduled outage and NukeWorker's model Projection -- is part of a subscription. Colored by status. How far ahead you can see depends on your plan.
Oct2025NovDecJan2026FebMarAprMayJunJulAugSepOnline: Sep 3, 2025 to Sep 24, 2025Scram: Sep 25, 2025 to Sep 26, 2025Reduced Power: Sep 27, 2025Online: Sep 28, 2025 to Aug 22, 2026Reduced Power: Aug 23, 2026 to Aug 24, 2026Online: Aug 25, 2026 to Sep 3, 2026Scram (reactor trip): Sep 24, 2025Today
OnlineReduced PowerScramScram (reactor trip)
Full history & analysis →
?
Composite Operational Excellence Score for Comanche Peak 1 — average percentile rank across 7 publicly observable metrics in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). Toggle the time window (3yr / 5yr / Lifetime) to see how this unit's standing shifts. Each dimension percentile-ranked across the active US fleet. Sub-score = average of components. Composite = average of the three sub-scores.

NukeWorker's Operational Excellence Score 5-yr composite · ranks 35 of 93

NukeWorker scores Comanche Peak 1's operational excellence at 53 out of 100 over the past five years, ranking it 35 of 93 reactors in the active US fleet. The score blends reliability, efficiency, and operating discipline drawn from public performance data.
Time window
5-yr trend: 2021: 71/100 (#20/93)2022: 56/100 (#39/92)2023: 47/100 (#50/92)2024: 53/100 (#39/92)2025: 50/100 (#46/92)2026: 50/100 (#41/93) Stable vs 2025
Compare Comanche Peak 1 head-to-head with up to 3 other units. Compare now

Capacity Factor (365-Day)

?
100%
Current
99%
365-Day Avg
#21
of 94 plants
Min: 0% Max: 100% 5 days <80%

Outage Duration Trend

?
Scheduled refueling outage durations over time. Green bars are below average, yellow near average, red above. Dashed line shows the plant's historical average. Shorter outages mean better execution.
Comanche Peak 1 has completed 18 scheduled refueling outages on record, averaging 32 days each. The most recent, in Apr 2025, ran 24 days.

Power History (12-Month)

?
Daily power output as a percentage of rated capacity over the past 365 days. Green segments indicate full power (90%+), yellow shows reduced output, and red indicates significant power reductions or shutdowns.
Over the past 12 months Comanche Peak 1 has run at an average of 99% of rated power. On the chart, green stretches are full-power running and dips toward zero mark reduced output or outages.

Outage Days by Year

?
Total days spent in outage each year, split by scheduled refueling (blue) and forced/unplanned (red). Lower totals indicate better reliability and outage execution. Hover for details.
Across its recorded history, Comanche Peak 1 has spent 574 days in scheduled refueling outages and 78 days in forced or unplanned outages. Taller bars mark the years with the most downtime.

Facility Statistics

?
Key performance and lifecycle metrics calculated from NRC operational data. Includes operating age, construction timeline, capacity factor, efficiency, generation totals, and reliability records.
Comanche Peak 1 has operated for about 36.1 years and averaged a 92.7% lifetime capacity factor, generating roughly 273.9 TWh of electricity. Its longest unbroken run reached 535 days.
Lifecycle & Tenure
Operating Age: 36.1 Yrs
Build Time: 15.6 Yrs
Lic. Remaining: 23.4 Yrs
Production & Power
Lifetime CF: 92.7%
Efficiency: 33.5%
Generated: 273.9 TWh
Reliability & Outages
Record Run: 535 Days
Refuelings: 18
Avg Startup: 7.5 Days

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Rural Route 1
Glen Rose, TX 76043, USA
Get Directions
Phone: (817) 897-8881
Website: http://txu.com

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from GSA for FY 2026.
$110
Lodging/Night
$68
M&IE/Day
$178
Total/Day
Standard Rate, TX

Unemployment Benefits TX

?
Maximum state unemployment insurance benefits for TX. Actual benefits depend on your earnings history and may be lower than the maximum. Data as of Jan 2026.
$605
Max Weekly
26
Max Weeks
$15,730
Max Total
7-day waiting period before benefits begin

Ownership & Construction

?
The utility or company that owns and operates the facility, the architect-engineer responsible for plant design, and the primary construction contractor. Click names to view all facilities by that entity on the map.
Owner/Operator: Vistra Corp.
Architect Engineer: G&H
Constructor: BRRT
VST Vistra Corp. NYSE
$143.81 ▲ +0.34 (+0.24%)
Previous Close 143.46
Day's Range 142.81 – 148.78
52-Week Range 132.66 – 219.82
Volume 3,353,740
Delayed quote as of Sep 3, 2026 3:36 PM ET. Source: Yahoo Finance. Full quote on Yahoo Finance

Technical Specs

?
Reactor design specifications including type (PWR/BWR), containment design, nuclear steam supply system manufacturer, thermal and electrical power ratings, and current operational status.
Reactor Type: PWR
Containment: PWR-DRYAMB
NSS Supplier: WEST 4LP
Thermal Power: 3612 MWt
Net Capacity: 1209 MWe
Efficiency: 33.5%
Status: Operating

Licensing

?
NRC licensing history including docket number, license type and number, construction permit date, operating license issuance, commercial operation date, license renewal, and expiration date.
Docket #: 05000445
License #: NPF-87
License Type: OL-FP
Const. Permit: 1974-12-19
Operating Lic: 1990-04-17
Commercial Op: 1990-08-13
License Renewed: 2024-07-30
License Exp: 2050-02-08

Market & Region

?
EIA market and grid-region classifications: NERC reliability region, U.S. Census region, balancing authority responsible for grid operations, and whether the unit operates as a rate-regulated utility or a competitive merchant generator. Hover any value for the full name.
NERC Region: TRE — Texas Regional Entity
Census Region: WSC — West South Central
Balancing Authority: ERCO — Electric Reliability Council of Texas (ERCOT) (ISO/RTO)
Market Structure: Merchant — Competitive generator selling into wholesale markets