Projection Explanation: Hatch 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 728.0 -46.28 days
Containment Type BWR-MARK 1 +26.39 days
Month 1.0 -13.07 days
Years to License Expiration 6.5 +9.62 days
Prior Cycle Length (months) 23.9 +4.57 days
Fleet Outages This Year 2.0 +3.13 days
Reactor Type (NSSS) GE 4 +2.95 days
unit_pct_in_predicted_month 0.0 -2.88 days
Units at Site 2.0 -2.44 days
unit_pct_in_spring_fall 0.2 +2.29 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?