Prediction Explanation: Hatch 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 742.0 -58.47 days
Containment Type BWR-MARK 1 +27.35 days
Reactor Type (NSSS) GE 4 +6.02 days
Prior Cycle Length (months) 24.4 +5.3 days
unit_pct_in_predicted_month 0.6 +3.15 days
Units at Site 2.0 -2.86 days
unit_pct_in_winter 0.7 +1.44 days
Years Since Major Maintenance 17.3 +0.76 days
Fleet Outages This Year 2.0 +0.73 days
Avg Outages Between Major Maint. N/A +0.64 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?