Projection Explanation: Hatch 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 742.0 -57.27 days
Containment Type BWR-MARK 1 +26.93 days
Prior Cycle Length (months) 24.4 +5.08 days
Reactor Type (NSSS) GE 4 +3.74 days
unit_pct_in_predicted_month 0.6 +3.01 days
Units at Site 2.0 -2.32 days
unit_pct_in_spring_fall 0.3 +1.86 days
unit_pct_in_winter 0.7 +1.39 days
Years to License Expiration 11.3 -1.34 days
Fleet Outages This Year 2.0 +0.99 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?