Prediction Explanation: McGuire 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Containment Type PWR-ICECND -14.66 days
Cycle Length (days) 567.0 +8.96 days
Reactor Type (NSSS) WEST 4LP -8.57 days
Prior Cycle Length (months) 18.6 -6.51 days
Net Capacity (MWe) 1158.0 -1.96 days
State NC +1.86 days
Balancing Authority DUK +1.86 days
Years to License Expiration 15.5 -1.54 days
Licensed Capacity (MWt) 3411.0 -1.01 days
Units at Site 2.0 -0.96 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?