Online NRC data, Mon to Fri ? Actual daily reactor status from NRC reports (Mon to Fri) and the current state. What is coming -- the utility's published Scheduled outage and NukeWorker's model Projection -- is part of a subscription. Colored by status. How far ahead you can see depends on your plan.
Nov2025DecJan2026FebMarAprMayJunJulAugSepOctNovOnline: Oct 24, 2025 to Mar 17, 2026Coastdown: Mar 18, 2026 to Mar 21, 2026Refueling Outage (M2R30): Mar 22, 2026 to Apr 18, 2026M2R30Power Ascension: Apr 19, 2026 to Apr 26, 2026Online: Apr 27, 2026 to Oct 24, 2026Today
OnlineCoastdownPower AscensionRefueling Outage
?
Composite Operational Excellence Score (0-100) — average percentile rank across 7 dimensions in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). 5-year window. Higher = more operationally excellent. Click to see the full breakdown.
   
Excellence
Rank locked · 93 units
Subscribers
?
Days of continuous operation since the last outage ended (Started 2026-04-18). Clean run (no forced outages since last refueling).
189
Current Run
days ✔
?
Longest recorded period of continuous operation between outages (2011-04-04 to 2012-09-16).
531
Record Run
days
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold set for this unit with no trips to 0% power.
12
B2B Runs
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power).
91.8%
Capacity Factor
?
Net electricity actually generated over the most recent 12 months reported by the U.S. EIA (Form EIA-923), summed across every unit at this plant. Authoritative actuals, not an estimate.
19 TWh
Net Generation
EIA-923 · 12 mo to 2026-07 · plant total
?
Total number of scheduled refueling outages detected in the historical data.
19
Outages
since 1999
?
Average time from first power generation (>0%) to sustained full power (≥95% for 2+ days) across the last 3 scheduled outages. Click to compare against the fleet on the Operator Efficiency Leaderboard.
6
Avg Startup
days (last 3)
?
Average fuel utilization — percent of the designed fuel cycle that this unit consumes before refueling, derived from the historical burn-down trajectory. Higher = more efficient operator (refuels with less margin remaining; closer to coastdown). Computed as 100% minus the unit's average refuel-point fuel %, using the last 3 years where available, otherwise lifetime average. Click to compare against the fleet on the Operator Efficiency Leaderboard.
99.6%
Fuel Utilization
3yr avg

Reactor Status

Capacity Factor (365-Day)

?
100%
Current
90.7%
365-Day Avg
#69
of 94 plants
Min: 0% Max: 100% 35 days <80%

Outage Days by Year

?
Total days spent in outage each year, split by scheduled refueling (blue) and forced/unplanned (red). Lower totals indicate better reliability and outage execution. Hover for details.
Across its recorded history, McGuire 2 has spent 675 days in scheduled refueling outages and 45 days in forced or unplanned outages. Taller bars mark the years with the most downtime.
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.

Outage Duration Trend

McGuire 2 has 31 outages plotted here, averaging 23 days each. The most recent, in Mar 2026, was a scheduled refueling outage lasting 28 days.
?
Scheduled refueling outage durations over time. Green bars are at or below this unit's average, amber up to 30% above it, red beyond that. The dashed line is the average. Shorter outages mean better execution.

Refueling Duration Trend

McGuire 2 has completed 19 scheduled refueling outages on record, averaging 36 days each. The most recent, in Mar 2026, ran 28 days.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.

Startup Duration Trend

After a refueling outage, McGuire 2 takes about 5 days to climb from first power back to full power. That average is drawn from 19 startups on record, and the most recent took 7 days.
?
Daily reactor power over the 120 days before each scheduled refueling outage, one line per refueling, lined up on the day the outage began. A coastdown is the slow decline as the fuel runs out near the end of a cycle. The highlighted line is the most recent refueling and fainter lines are older. Counts and medians cover coastdowns of a week or longer. A shutdown straight from full power, with no decline ahead of it, is what a forced outage looks like.

Coastdown Before Refueling

6 of 19 refuelings 19 days median 89% power at shutdown 0.4% per day
McGuire 2 coasted down for a week or longer before 6 of its 19 refuelings on record. Those coastdowns ran a median of 19 days and ended near 89% power. The most recent refueling, in Mar 2026, began with no extended coastdown.
?
Estimated fuel remaining in the current cycle, expressed as a percentage of the unit's typical cycle. Starts at 100% when the unit returns to power post-refuel and drops as full-power-days are burned. Days at reduced power burn fuel proportionally — so a unit with significant downtime (high burn deficit) drops slower and ends up with MORE fuel left than its calendar position would suggest. Coastdown threshold around 15%. Toggle to overlay past cycles on a normalized "days into cycle" axis to see how aggressively this unit historically burns down before refuel.

Fuel Burn Down Cycle since Apr 20, 2026

64.5% remaining 3.0 FPD margin
McGuire 2 has an estimated 64.5% of its fuel left. Across its last 18 cycles, it has refueled with an average of 2.8% remaining.
Avg refuel: 2.8% Avg refuel (3yr): 0.4% Deepest burn: 0.0% (2002-03 → 2003-09) Most margin: 8.8% (2012-11 → 2014-03)
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.

Power History

Over its operating life, McGuire 2 has run at about 91.8% of its rated capacity. Across the last 12 reported months it averaged 90.7%. On the chart, green stretches near the top are full-power running, amber marks reduced power (50 to 89%), and red drops toward zero are outages.

Outage History & Daily Power Log

This table logs every recorded outage for McGuire 2, 31 in all since 1999. Of those, 19 were scheduled refueling outages and 12 were unplanned or forced. The typical outage lasted about 23 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
Scheduled M2R30
2026-03-22 2026-04-18 28 157d 2026-03-21 +1d
Scram # 57977 Manual
2025-10-10 2025-10-16 7 384d - -
Scheduled M2R29
2024-09-01 2024-09-21 21 517d 2024-09-01 0d
Scheduled M2R28
2023-02-18 2023-04-03 45 362d 2023-02-18 0d
Scram # 55748 Manual
2022-02-19 2022-02-21 3 132d - -
Scheduled M2R27
2021-09-11 2021-10-10 30 516d 2021-09-11 0d
Scheduled M2R26
2020-03-21 2020-04-13 24 526d 2020-03-14 +7d
Scheduled M2R25
2018-09-15 2018-10-12 28 511d 2018-09-15 0d
Scheduled M2R24
2017-03-30 2017-04-22 24 22d 2017-03-30 0d
Unscheduled
2017-02-24 2017-03-08 13 504d - -
Scheduled M2R23
2015-09-13 2015-10-09 27 508d 2015-09-12 +1d
Scheduled M2R22
2014-03-22 2014-04-23 33 477d 2014-03-22 0d
Unscheduled
2012-11-28 2012-11-30 3 6d - -
Scheduled M2R21SGR/Major
2012-09-16 2012-11-22 68 531d 2012-09-15 +1d
Scheduled M2R20
2011-02-27 2011-04-04 37 33d 2011-03-05 -6d
Unscheduled
2011-01-21 2011-01-25 5 468d - -
Scheduled M2R19
2009-09-06 2009-10-10 35 508d 2009-09-05 +1d
Unscheduled
2008-04-14 2008-04-16 3 2d - -
Scheduled M2R18
2008-03-02 2008-04-12 42 479d 2008-03-01 +1d
Scheduled M2R17
2006-09-17 2006-11-09 54 515d 2006-09-16 +1d
Unscheduled
2005-04-18 2005-04-20 3 2d - -
Unscheduled
2005-04-15 2005-04-16 2 2d - -
Scheduled M2R16
2005-03-02 2005-04-13 43 514d 2005-03-01 +1d
Scheduled M2R15
2003-09-06 2003-10-05 30 378d 2003-09-06 0d
Unscheduled
2002-08-23 2002-08-24 2 150d - -
Scheduled M2R14
2002-02-23 2002-03-26 32 220d 2002-02-23 0d
Unscheduled
2001-07-17 2001-07-18 2 243d - -
Unscheduled
2000-11-16 2000-11-16 1 35d - -
Scheduled M2R13
2000-09-02 2000-10-12 41 414d 2000-09-02 0d
Unscheduled
1999-07-16 1999-07-16 1 93d - -
Scheduled M2R12
1999-03-13 1999-04-14 33 - 1999-03-13 0d