Projection Explanation: Millstone 3

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 549.0 +13.64 days
Containment Type PWR-DRYSUB -9.33 days
Reactor Type (NSSS) WEST 4LP -4.11 days
State CT -2.43 days
Units at Site 2.0 -1.58 days
Licensed Capacity (MWt) 3650.0 -1.09 days
Balancing Authority ISNE -1.04 days
Net Capacity (MWe) 1243.0 -1.01 days
Outage Number (experience) 18.0 -0.95 days
Avg Coastdown Days (this unit) 14.7 +0.63 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?