Projection Explanation: Oconee 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
731.0 |
-31.03 days |
| Reactor Type (NSSS) |
B&W LLP |
+14.59 days |
| State |
SC |
+5.63 days |
| Age at Outage (years) |
53.1 |
-5.59 days |
| Prior Cycle Length (months) |
24.1 |
+4 days |
| Containment Type |
PWR-DRYAMB |
-3.85 days |
| unit_pct_in_predicted_month |
0.6 |
+2.65 days |
| Balancing Authority |
DUK |
+2.51 days |
| Licensed Capacity (MWt) |
2610.0 |
+2.05 days |
| Years to License Expiration |
25.9 |
-1.58 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?