Projection Explanation: Oconee 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 731.0 -31.03 days
Reactor Type (NSSS) B&W LLP +14.59 days
State SC +5.63 days
Age at Outage (years) 53.1 -5.59 days
Prior Cycle Length (months) 24.1 +4 days
Containment Type PWR-DRYAMB -3.85 days
unit_pct_in_predicted_month 0.6 +2.65 days
Balancing Authority DUK +2.51 days
Licensed Capacity (MWt) 2610.0 +2.05 days
Years to License Expiration 25.9 -1.58 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?

Page created in 0.007 seconds with 0 queries.