Projection Explanation: Palo Verde 3
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
546.0 |
+14.22 days |
| Containment Type |
PWR-DRYAMB |
-9.04 days |
| State |
AZ |
-5.41 days |
| Reactor Type (NSSS) |
COMB CE80 |
+2.6 days |
| NRC Region |
4.0 |
-2.19 days |
| Units at Site |
3.0 |
-1.34 days |
| Outage Number (experience) |
18.0 |
-1.31 days |
| Age at Outage (years) |
39.2 |
+1.27 days |
| Avg Coastdown Days (this unit) |
6.0 |
-0.67 days |
| Avg Outages Between Major Maint. |
3.5 |
-0.63 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?