Projection Explanation: Robinson 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Net Capacity (MWe) 759.0 +16.89 days
Cycle Length (days) 717.0 -16.26 days
Balancing Authority CPLE +10.32 days
Age at Outage (years) 55.7 -7.9 days
Licensed Capacity (MWt) 2339.0 +7.85 days
Units at Site 1.0 +6.28 days
State SC +4.34 days
Containment Type PWR-DRYAMB -3.69 days
Avg Outages Between Major Maint. 1.7 -3.34 days
Reactor Type (NSSS) WEST 3LP +3.31 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?