Projection Explanation: Sequoyah 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
794.0 |
-71.39 days |
| Previous Outage Duration |
290.0 |
-19.24 days |
| Reactor Type (NSSS) |
WEST 4LP |
-15.43 days |
| Containment Type |
PWR-ICECND |
-5.48 days |
| State |
TN |
+4.92 days |
| Forced Outage Days in Cycle |
33.0 |
-4.15 days |
| unit_pct_in_predicted_month |
0.3 |
+3.85 days |
| Prior Cycle Length (months) |
26.1 |
+2.7 days |
| unit_modal_month |
4.0 |
+2.43 days |
| Units at Site |
2.0 |
-2.06 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?