Prediction Explanation: Vogtle 1

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 532.0 +28.47 days
Containment Type PWR-DRYAMB -7.44 days
Reactor Type (NSSS) WEST 4LP -4.62 days
Prior Cycle Length (months) 17.5 -3.36 days
Units at Site 4.0 -1.42 days
State GA -1.22 days
Years to License Expiration 19.4 -1.18 days
unit_pct_in_predicted_month 0.0 -0.99 days
Fleet Outages This Year 2.0 +0.63 days
Avg Outages Between Major Maint. N/A +0.6 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?