North Anna 1

Online · 100% power

Dominion Energy·Mineral, VA·PWR·948 MWe

Data refreshed 1.1h ago Rx Status: Oct 19, 2026 at 5:12 AM (M-F)

Reactor Status Timeline

Online NRC data, Mon to Fri ? Actual daily reactor status from NRC reports (Mon to Fri) and the current state. What is coming -- the utility's published Scheduled outage and NukeWorker's model Projection -- is part of a subscription. Colored by status. How far ahead you can see depends on your plan.
Nov2025DecJan2026FebMarAprMayJunJulAugSepOctNovPower Ascension: Oct 19, 2025 to Oct 21, 2025Scram: Oct 22, 2025 to Oct 24, 2025Power Ascension: Oct 25, 2025 to Oct 27, 2025Online: Oct 28, 2025 to Oct 19, 2026Scram (reactor trip): Oct 21, 2025Today
OnlinePower AscensionScram⚡Scram (reactor trip)
?
Composite Operational Excellence Score (0-100) — average percentile rank across 7 dimensions in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). 5-year window. Higher = more operationally excellent. Click to see the full breakdown.
   
Excellence
Rank locked · 93 units
Subscribers
?
Days of continuous operation since the last outage ended (Started 2025-10-24). Clean run (no forced outages since last refueling).
360
Current Run
days ✔
?
Longest recorded period of continuous operation between outages (2019-09-30 to 2021-03-14).
531
Record Run
days
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold set for this unit with no trips to 0% power.
9
B2B Runs
79% toward B2B (356/449d)
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power).
91.2%
Capacity Factor
?
Net electricity actually generated over the most recent 12 months reported by the U.S. EIA (Form EIA-923), summed across every unit at this plant. Authoritative actuals, not an estimate.
15.85 TWh
Net Generation
EIA-923 · 12 mo to 2026-07 · plant total
?
Total number of scheduled refueling outages detected in the historical data.
18
Outages
since 2000
?
Average time from first power generation (>0%) to sustained full power (≥95% for 2+ days) across the last 3 scheduled outages. Click to compare against the fleet on the Operator Efficiency Leaderboard.
5
Avg Startup
days (last 3)
?
Average fuel utilization — percent of the designed fuel cycle that this unit consumes before refueling, derived from the historical burn-down trajectory. Higher = more efficient operator (refuels with less margin remaining; closer to coastdown). Computed as 100% minus the unit's average refuel-point fuel %, using the last 3 years where available, otherwise lifetime average. Click to compare against the fleet on the Operator Efficiency Leaderboard.
99.7%
Fuel Utilization
3yr avg

Reactor Status

Capacity Factor (365-Day)

?
100%
Current
98.6%
365-Day Avg
#28
of 94 plants
Min: 0% Max: 100% 7 days <80%

Outage Days by Year

?
Total days spent in outage each year, split by scheduled refueling (blue) and forced/unplanned (red). Lower totals indicate better reliability and outage execution. Hover for details.
Across its recorded history, North Anna 1 has spent 621 days in scheduled refueling outages and 163 days in forced or unplanned outages. Taller bars mark the years with the most downtime.
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.

Outage Duration Trend

North Anna 1 has 38 outages plotted here, averaging 21 days each. The most recent, in Oct 2025, was a unplanned outage lasting 3 days.
?
Scheduled refueling outage durations over time. Green bars are at or below this unit's average, amber up to 30% above it, red beyond that. The dashed line is the average. Shorter outages mean better execution.

Refueling Duration Trend

North Anna 1 has completed 18 scheduled refueling outages on record, averaging 35 days each. The most recent, in Sep 2025, ran 42 days.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.

Startup Duration Trend

After a refueling outage, North Anna 1 takes about 4 days to climb from first power back to full power. That average is drawn from 18 startups on record, and the most recent took 8 days.
?
Daily reactor power over the 120 days before each scheduled refueling outage, one line per refueling, lined up on the day the outage began. A coastdown is the slow decline as the fuel runs out near the end of a cycle. The highlighted line is the most recent refueling and fainter lines are older. Counts and medians cover coastdowns of a week or longer. A shutdown straight from full power, with no decline ahead of it, is what a forced outage looks like.

Coastdown Before Refueling

8 of 18 refuelings 13 days median 88% power at shutdown 0.6% per day
North Anna 1 coasted down for a week or longer before 8 of its 18 refuelings on record. Those coastdowns ran a median of 13 days and ended near 88% power. The most recent refueling, in Sep 2025, followed a 13-day coastdown from 97% to 89%.
?
Estimated fuel remaining in the current cycle, expressed as a percentage of the unit's typical cycle. Starts at 100% when the unit returns to power post-refuel and drops as full-power-days are burned. Days at reduced power burn fuel proportionally — so a unit with significant downtime (high burn deficit) drops slower and ends up with MORE fuel left than its calendar position would suggest. Coastdown threshold around 15%. Toggle to overlay past cycles on a normalized "days into cycle" axis to see how aggressively this unit historically burns down before refuel.

Fuel Burn Down Cycle since Oct 19, 2025

29.7% remaining 4.5 FPD margin
North Anna 1 has an estimated 29.7% of its fuel left. Across its last 17 cycles, it has refueled with an average of 3.3% remaining.
Avg refuel: 3.3% Avg refuel (3yr): 0.3% Deepest burn: 0.0% (2009-04 → 2010-09) Most margin: 20.3% (2010-10 → 2012-03)
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.

Power History

Over its operating life, North Anna 1 has run at about 91.2% of its rated capacity. Across the last 12 reported months it averaged 100.0%. On the chart, green stretches near the top are full-power running, amber marks reduced power (50 to 89%), and red drops toward zero are outages.

Outage History & Daily Power Log

This table logs every recorded outage for North Anna 1, 38 in all since 2000. Of those, 18 were scheduled refueling outages and 20 were unplanned or forced. The typical outage lasted about 21 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
Scram # 57997 Auto
2025-10-22 2025-10-24 3 4d - -
Scheduled 1R31
2025-09-07 2025-10-18 42 464d 2025-09-01 +6d
Scram # 57148 Auto
2024-05-30 2024-05-31 2 54d - -
Scheduled 1R30
2024-03-03 2024-04-06 35 159d 2024-03-02 +1d
Unscheduled
2023-09-25 2023-09-26 2 334d - -
Scheduled 1R29
2022-09-21 2022-10-26 36 158d 2022-09-11 +10d
Scram # 55843 Auto
2022-04-15 2022-04-16 2 208d - -
Unscheduled
2021-09-12 2021-09-19 8 118d - -
Scram # 55239 Manual
2021-05-07 2021-05-17 11 15d - -
Scheduled 1R28
2021-03-14 2021-04-22 40 531d 2021-03-06 +8d
Scheduled 1R27
2019-09-08 2019-09-30 23 511d 2019-09-02 +6d
Scheduled 1R26
2018-03-11 2018-04-15 36 512d 2018-03-11 0d
Scheduled 1R25
2016-09-11 2016-10-15 35 526d 2016-09-11 0d
Scram # 50946 Manual
2015-04-02 2015-04-04 3 5d - -
Scheduled 1R24
2015-03-08 2015-03-28 21 8d 2015-03-08 0d
Scram # 50851 Auto
2015-02-27 2015-02-28 2 57d - -
Unscheduled
2014-12-23 2015-01-01 10 436d - -
Scram # 49429 Auto
2013-10-12 2013-10-13 2 2d - -
Scheduled 1R23
2013-09-08 2013-10-10 33 496d 2013-09-08 0d
Scheduled 1R22
2012-03-11 2012-04-30 51 119d 2012-03-11 0d
Scram # 47181 Auto
2011-08-24 2011-11-13 82 307d - -
Scheduled 1R21
2010-09-12 2010-10-21 40 56d 2010-09-12 0d
Unscheduled
2010-07-15 2010-07-18 4 259d - -
Unscheduled
2009-10-24 2009-10-29 6 205d - -
Scheduled 1R20
2009-03-08 2009-04-02 26 511d 2009-03-08 0d
Scheduled 1R19
2007-09-09 2007-10-14 36 248d 2007-09-09 0d
Unscheduled
2007-01-04 2007-01-04 1 49d - -
Unscheduled
2006-11-13 2006-11-16 4 218d - -
Scheduled 1R18
2006-03-12 2006-04-09 29 24d 2006-03-11 +1d
Unscheduled
2006-02-14 2006-02-16 3 496d - -
Scheduled 1R17
2004-09-12 2004-10-06 25 199d 2004-09-12 0d
Unscheduled
2004-02-21 2004-02-26 6 246d - -
Unscheduled
2003-06-12 2003-06-20 9 53d - -
Unscheduled
2003-04-20 2003-04-20 1 2d - -
Scheduled 1R16
2003-02-23 2003-04-18 55 502d 2003-02-23 0d
Scheduled 1R15
2001-09-09 2001-10-09 31 488d 2001-09-09 0d
Unscheduled
2000-05-08 2000-05-09 2 31d - -
Scheduled 1R14
2000-03-12 2000-04-07 27 - 2000-03-12 0d