B2B CHAMPION
1,226 days without a trip
·
1 Career Run · 1 since last trip
Champion since Aug 10, 2026
Breaker-to-Breaker Runs
1 run
?
Breaker-to-breaker runs measure continuous operation between refueling outages using a cycle-adjusted threshold (90% of cycle length minus RFO duration). An active streak means the unit has been running continuously since the last refueling with no trips to 0% power.
Robinson 2 has logged 1 breaker-to-breaker run, continuous stretches from one refueling to the next with no trip to zero power. Its longest ran 666 days, and its runs average 666 days.
666
Best Run (days)
RO-34 (2024-12-06) → RO-35 (2026-10-03)
About This Site
?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: H. B. Robinson Nuclear Generating Station.
H. B. Robinson Steam Electric Plant is near Hartsville in Darlington County, South Carolina. It sits beside Lake Robinson, a lake of about 2,250 acres that serves as its cooling source.
Read more
The site holds Unit 2, a Westinghouse three-loop pressurized water reactor. Construction began on April 13, 1967, the unit was first connected to the grid on September 26, 1970, and commercial operation began on March 7, 1971. The plant is described as the first commercial nuclear plant in the southeastern United States. The site also had a coal-fired Unit 1, which was retired in October 2012 and demolished in 2016.
Facility Statistics
?
Key performance and lifecycle metrics calculated from NRC operational data. Includes operating age, construction timeline, capacity factor, efficiency, generation totals, and reliability records.
Robinson 2 has operated for about 55.7 years and averaged a 89.6% lifetime capacity factor, generating roughly 164.9 TWh of electricity. Its longest unbroken run reached 714 days.
Lifecycle & Tenure
Operating Age: 55.7 Yrs
Build Time: 3.9 Yrs
Lic. Remaining: 23.7 Yrs
Production & Power
Lifetime CF: 89.6%
Efficiency: 32.4%
Generated: 164.9 TWh
Reliability & Outages
Record Run: 714 Days
Refuelings: 17
Avg Startup: 4.7 Days
Ownership & Construction
?
The utility or company that owns and operates the facility, the architect-engineer responsible for plant design, and the primary construction contractor. Click names to view all facilities by that entity on the map.
Ownership, operation and management history
| Date | Change |
From | To |
| Nov 30, 2000 |
Merger |
Carolina Power & Light |
Progress Energy |
| Jul 2, 2012 |
Merger |
Progress Energy |
Duke Energy |
DUK
Duke Energy Corporation
NYSE
$127.39
▲ +1.49 (+1.18%)
Previous Close
125.90
Day's Range
126.54 – 128.07
52-Week Range
112.40 – 134.49
Volume
4,907,212
Operational Excellence Score Subscribers
Robinson 2 is rated 0 to 100 on how well it actually runs, scored against every other operating reactor in the US fleet from its own operating record. Subscribers see the score, the three sub-scores behind it, and each of the seven measured inputs.
- This unit's composite score and fleet rank
- Reliability, Efficiency and Discipline sub-scores
- All seven measured inputs, with fleet percentiles
- Rank against comparable units, not just the fleet
- Three-year, five-year and lifetime windows
- Five-year trend, and every other operating US reactor
Scram History
8 events since 2011
?
Automatic and manual reactor scram (emergency shutdown) events reported to the NRC since 2011. Includes event dates, trip type, and average recovery time. Click the title to view the full fleet scram dashboard.
Robinson 2 has recorded 8 reactor scrams, or emergency shutdowns, since 2011 (8 automatic, 0 manual). On average the unit was back to full power about 8.9 days after each trip.
Recent Events
| 2023-06-22 |
Auto |
EN Revision Imported Date: 6/27/2023 EN Revision Text: AUTOM... |
|
| 2019-08-11 |
Auto |
AUTOMATIC REACTOR TRIP DUE TO TURBINE TRIP "At 0840 EDT, on ... |
|
| 2016-10-08 |
Auto |
UNUSUAL EVENT DECLARED DUE TO LOSS OF OFFSITE POWER "UE SU1.... |
|
| 2016-08-24 |
Auto |
REACTOR TRIP DUE AUTOMATIC TURBINE TRIP FROM 100 PERCENT POW... |
|
| 2014-01-09 |
Auto |
AUTOMATIC REACTOR TRIP DUE TO TURBINE TRIP "At 2234 hours ES... |
|
| 2013-11-05 |
Auto |
AUTOMATIC REACTOR TRIP DUE TO MOMENTARY LOSS OF 4 KV BUSES A... |
|
| 2012-03-28 |
Auto |
AUTOMATIC REACTOR TRIP DUE TO STEAM GENERATOR HIGH WATER LEV... |
|
| 2011-09-26 |
Auto |
AUTOMATIC REACTOR TRIP DUE TO ONE LOOP LOW FLOW SIGNAL "At 1... |
|
Technical Specs
?
Reactor design specifications including type (PWR/BWR), containment design, nuclear steam supply system manufacturer, thermal and electrical power ratings, and current operational status.
Turbine Supplier:
WESTINGHOUSE ELECTRIC CORPORATION IAEA
Thermal Power:
2339 MWt
Net Capacity:
759 MWe
Gross Capacity:
780 MWe IAEA
Design Capacity:
700 MWe IAEA
Efficiency:
32.4%
Lifetime Output:
272.7 TWh through 2025 IAEA
Licensing
?
NRC licensing history including docket number, license type and number, construction permit date, operating license issuance, commercial operation date, license renewal, and expiration date.
Docket #:
05000261
License #:
DPR-23
License Type:
OL-FP
Const. Permit:
1967-04-13
Construction Start:
1967-04-13 IAEA
Operating Lic:
1970-07-31
First Criticality:
1970-09-20 IAEA
Grid Connection:
1970-09-26 IAEA
Commercial Op:
1971-03-07
License Renewed:
2026-04-23
License Exp:
2050-07-31
Market & Region
?
EIA market and grid-region classifications: NERC reliability region, U.S. Census region, balancing authority responsible for grid operations, and whether the unit operates as a rate-regulated utility or a competitive merchant generator. Hover any value for the full name.
NERC Region:
SERC
— SERC Reliability Corporation
Census Region:
SAT
— South Atlantic
Balancing Authority:
CPLE
— Duke Energy Progress East (formerly Carolina Power & Light - East)
Market Structure:
Regulated
— Rate-regulated utility (cost-of-service pricing)