San Onofre 3 — Decommissioned Reactor Data & History

Operational history, outage history & performance charts, scram history, capacity factor & statistics, community ratings, technical specifications, NRC licensing data, photos, nearby jobs, satellite map, contact information, and per diem rates for San Onofre 3.

Decommissioned

Permanently shut down on 2012-01-31. View Outage History →
?
Current reactor power level from the most recent NRC daily report.
Shut Down
?
Days of continuous operation since the last outage ended. Ranked against all operating units.
4,743
Current Run
days
?
Longest recorded period of continuous operation between outages.
4,743
Record Run
days
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold (532 days for this 24-month cycle unit) with no trips to 0% power.
2
B2B Runs
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power). Ranked against all NRC-tracked units.
74.8%
Capacity Factor
?
Community rating score (Bayesian-adjusted). Based on 92 votes. Ranked against all rated facilities.
47.8
Rating
92 votes
#73 of 97
Mid Quartile
?
Total NRC-reported scram events (emergency reactor shutdowns). Ranked fleet-wide — fewer scrams = better rank.
2
Scrams
?
Years since commercial operation began.
27.8
Operating Age
years

Outage Duration Trend

?
Scheduled refueling outage durations over time. Green bars are below average, yellow near average, red above. Dashed line shows the plant's historical average. Shorter outages mean better execution.
San Onofre 3 has completed 4 scheduled refueling outages on record, averaging 85 days each. The most recent, in Oct 2010, ran 130 days.

Outage Days by Year

?
Total days spent in outage each year, split by scheduled refueling (blue) and forced/unplanned (red). Lower totals indicate better reliability and outage execution. Hover for details.
Across its recorded history, San Onofre 3 has spent 340 days in scheduled refueling outages and 359 days in forced or unplanned outages. Taller bars mark the years with the most downtime.

Facility Statistics

?
Key performance and lifecycle metrics calculated from NRC operational data. Includes operating age, construction timeline, capacity factor, efficiency, generation totals, and reliability records.
San Onofre 3 has operated for about 27.8 years and averaged a 74.8% lifetime capacity factor, generating roughly 102.9 TWh of electricity. Its longest unbroken run reached 4,743 days.
Lifecycle & Tenure
Operating Age: 27.8 Yrs
Build Time: 10.5 Yrs
Lic. Remaining: N/A Yrs
Production & Power
Lifetime CF: 74.8%
Efficiency: 31.9%
Generated: 102.9 TWh
Reliability & Outages
Record Run: 4,743 Days
Refuelings: 4
Avg Startup: 12.8 Days

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
5000 Pacific Coast Highway
San Clemente, CA 92673, USA
Get Directions
Phone: (714) 302-1212

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from GSA for FY 2026.
$191
Lodging/Night
$86
M&IE/Day
$277
Total/Day
Los Angeles, Los Angeles / Orange / Ventura / Edwards AFB less the city of Santa Monica County, CA

Unemployment Benefits CA

?
Maximum state unemployment insurance benefits for CA. Actual benefits depend on your earnings history and may be lower than the maximum. Data as of Jan 2026.
$450
Max Weekly
26
Max Weeks
$11,700
Max Total
7-day waiting period before benefits begin

Ownership & Construction

?
The utility or company that owns and operates the facility, the architect-engineer responsible for plant design, and the primary construction contractor. Click names to view all facilities by that entity on the map.
Architect Engineer: BECH
Constructor: BECH

Technical Specs

?
Reactor design specifications including type (PWR/BWR), containment design, nuclear steam supply system manufacturer, thermal and electrical power ratings, and current operational status.
Reactor Type: PWR
Containment: PWR-DRYAMB
NSS Supplier: COMB CE
Thermal Power: 3390 MWt
Net Capacity: 1080 MWe
Efficiency: 31.9%

Licensing

?
NRC licensing history including docket number, license type and number, construction permit date, operating license issuance, commercial operation date, license renewal, and expiration date.
Docket #: 05000362
License #: NPF-15
License Type: OL-FP
Const. Permit: 1973-10-18
Operating Lic: 1983-09-16
Commercial Op: 1984-04-01
License Exp: 2013-10-18