Projection Explanation: Calvert Cliffs 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 735.0 -27.03 days
Years to License Expiration 6.5 +9.03 days
Prior Cycle Length (months) 24.2 +5.03 days
Reactor Type (NSSS) COMB CE +3.58 days
Containment Type PWR-DRYAMB -2.99 days
unit_pct_in_predicted_month 0.8 +2.47 days
unit_pct_in_winter 0.8 +1.63 days
Age at Outage (years) 52.8 -1.59 days
unit_pct_in_spring_fall 0.2 +1.51 days
Season winter -0.83 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?