Projection Explanation: Calvert Cliffs 1
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
735.0 |
-27.03 days |
| Years to License Expiration |
6.5 |
+9.03 days |
| Prior Cycle Length (months) |
24.2 |
+5.03 days |
| Reactor Type (NSSS) |
COMB CE |
+3.58 days |
| Containment Type |
PWR-DRYAMB |
-2.99 days |
| unit_pct_in_predicted_month |
0.8 |
+2.47 days |
| unit_pct_in_winter |
0.8 |
+1.63 days |
| Age at Outage (years) |
52.8 |
-1.59 days |
| unit_pct_in_spring_fall |
0.2 |
+1.51 days |
| Season |
winter |
-0.83 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?