Prediction Explanation: Clinton
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
728.0 |
-37.77 days |
| Containment Type |
BWR-MARK 3 |
+20.14 days |
| Units at Site |
1.0 |
+7.17 days |
| Reactor Type (NSSS) |
GE 6 |
+5.97 days |
| Prior Cycle Length (months) |
23.9 |
+3.49 days |
| Avg Outages Between Major Maint. |
N/A |
+2.99 days |
| State |
IL |
-1.47 days |
| Fleet Outages This Year |
8.0 |
-1.17 days |
| cycle_interval_cv |
0.2 |
-0.84 days |
| Day of Week |
1.0 |
+0.76 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?